2027 Maintenance Update

Where your $95-per-acre assessment is going this winter

This winter the District is replacing decades of patchwork on the “A” Canal deep cut with a repair built to last 50 to 100 years. Work is underway now, alongside an emergency repair of the “E” Canal siphon, so both are ready to carry water in the 2027 irrigation season. Combined, these two emergency repairs will consume several months and over $1.5 million of our farmers’ annual assessment for operations and maintenance; no grants awarded.

Keeping the District viable

Nov. 2026 Dec. 2025: no increase for 2026 2027 increase approved Safe reserve level Funds run out Without increase With yearly increase 202320242025202620272028202920302031

With no rate increase in 2026, District savings fell below the safe reserve level.

Without an increase, savings keep shrinking as costs rise until the money runs out.

With a steady, modest yearly increase, savings level off and stay positive. For 2027, the Directors approved an increase consistent with inflation in fuel, insurance and other costs.

What the District found, and the fix

“A” Canal deep cut

The concrete lining of the deep cut has reached the end of what patching can do. General Manager Jaxsen Sikorski inspected the full reach before work began and found:

  • wall panels that have failed or buckled at the base
  • large voids behind the lining, including behind earlier temporary repairs
  • long horizontal cracks and concrete sloughing into the channel

For years the District filled these voids with concrete bags laid like masonry. Water kept working in behind the patches, and the voids kept growing.

The drained A Canal deep cut with broken concrete lining along the right wall
The deep cut, drained for inspection, 30 October 2026.

What is being done. The walls will be relined with shotcrete: sprayed concrete five inches thick, reinforced with a double dose of fibre.

  • District crews built a new access road along the top of the cut for equipment and the concrete pump.
  • We contracted with Paul Bair to clear the vegetation from the top of the walls.
  • Crews are packing rock into the voids before the concrete goes on. Concrete is running $306 a yard, and every yard of rock saves a yard of concrete.
  • The goal is to finish before the end of 2026.
  • Project manager: Willy Stevens.

Proven last winter

The District relined a 780-foot section at the outlet of the “A” Canal tunnel the same way. After a full irrigation season, inspection found no cracking, no shrinkage and no scour.

A District truck in the drained canal between smooth, intact relined walls
Close view of the relined canal wall, with no cracks

The relined section after a full irrigation season, 30 October 2026.

Watch the work

The new maintenance road along the top of the cut. Watch on YouTube

The deep cut, November 2026. Watch on YouTube

Photos from the inspection, 30 October 2026

Select any photo to see it full size.

“E” Canal siphon

An excavator and dump truck at the E Canal siphon excavation

The failed “E” Canal siphon, which carries water toward North Poe Valley, is being replaced with new 48-inch pipe this winter. The District is working with ODOT, its contractors and the pipe manufacturer for the best long-term repair. The failure was anticipated, but not funded in the 2026 Budget; we thought we had 1-5 years to work with our partners and their budgets. Project manager: Nate Blevin.

Photos from the siphon excavation, October 2026

Ahead in 2027 and 2028

Beyond the two emergency repairs, staff proposed a shorter maintenance list for 2027 and held back what could wait until 2028, to keep costs down.

In 2027 and 2028, the District will be engaged with federal agencies and our communities to reconsult on the existing Endangered Species Act regulations, which are affecting our farming families without any measurable improvement to the species over the past 30 years.

Want updates?

Sign up to receive District updates by email.

Sign up for District updates

District office and meetings

District office

541-882-6661

6640 KID Lane
Klamath Falls, OR 97603

Hours: 8-4:30 M-F (closed holidays)

Annual Meeting

Thursday, 14 January 2027

1:00 p.m.
K.I.D. Conference Room

Read the meeting notice