2027 Maintenance Update
Where your $95-per-acre assessment is going this winter
This winter the District is replacing decades of patchwork on the “A” Canal deep cut with a repair built to last 50 to 100 years. Work is underway now, alongside an emergency repair of the “E” Canal siphon, so both are ready to carry water in the 2027 irrigation season. Combined, these two emergency repairs will consume several months and over $1.5 million of our farmers’ annual assessment for operations and maintenance; no grants awarded.
Keeping the District viable
With no rate increase in 2026, District savings fell below the safe reserve level.
Without an increase, savings keep shrinking as costs rise until the money runs out.
With a steady, modest yearly increase, savings level off and stay positive. For 2027, the Directors approved an increase consistent with inflation in fuel, insurance and other costs.
What the District found, and the fix
“A” Canal deep cut
The concrete lining of the deep cut has reached the end of what patching can do. General Manager Jaxsen Sikorski inspected the full reach before work began and found:
- wall panels that have failed or buckled at the base
- large voids behind the lining, including behind earlier temporary repairs
- long horizontal cracks and concrete sloughing into the channel
For years the District filled these voids with concrete bags laid like masonry. Water kept working in behind the patches, and the voids kept growing.
What is being done. The walls will be relined with shotcrete: sprayed concrete five inches thick, reinforced with a double dose of fibre.
- District crews built a new access road along the top of the cut for equipment and the concrete pump.
- We contracted with Paul Bair to clear the vegetation from the top of the walls.
- Crews are packing rock into the voids before the concrete goes on. Concrete is running $306 a yard, and every yard of rock saves a yard of concrete.
- The goal is to finish before the end of 2026.
- Project manager: Willy Stevens.
Watch the work
The new maintenance road along the top of the cut. Watch on YouTube
The deep cut, November 2026. Watch on YouTube
Photos from the inspection, 30 October 2026
Select any photo to see it full size.
“E” Canal siphon
The failed “E” Canal siphon, which carries water toward North Poe Valley, is being replaced with new 48-inch pipe this winter. The District is working with ODOT, its contractors and the pipe manufacturer for the best long-term repair. The failure was anticipated, but not funded in the 2026 Budget; we thought we had 1-5 years to work with our partners and their budgets. Project manager: Nate Blevin.
Photos from the siphon excavation, October 2026
Ahead in 2027 and 2028
Beyond the two emergency repairs, staff proposed a shorter maintenance list for 2027 and held back what could wait until 2028, to keep costs down.
In 2027 and 2028, the District will be engaged with federal agencies and our communities to reconsult on the existing Endangered Species Act regulations, which are affecting our farming families without any measurable improvement to the species over the past 30 years.
Want updates?
Sign up to receive District updates by email.
District office and meetings
District office
6640 KID Lane
Klamath Falls, OR 97603
Hours: 8-4:30 M-F (closed holidays)
Board meetings
Second Thursday, monthly
Typically 1:00 p.m.
K.I.D. Conference Room