Klamath Irrigation District · Annual Record

Water Year 2027

October 1, 2026 to September 30, 2027. This page opens the year and will be filled in as the year runs.

Status: Year opened 1 October 2026.

How to read this page

Water year. The accounting year runs from 1 October to 30 September. WY2027 is the year that begins 1 October 2026.

Acre-foot (AF). The amount of water that covers one acre one foot deep. About 325,851 gallons, or roughly three homes' water use for a year.

Cubic foot per second (cfs). A measure of flow speed, not volume. One cfs for a day is about 2 acre-feet, or about 450 gallons a minute.

Upper Klamath Lake (UKL). The lake that supplies the Project. Its level in feet above sea level is the number to watch.

Part 1 · How the 2027 season begins

01 Charts: WY2027 to date

These charts use the daily Reclamation record for 1 to 29 October 2026. One week is not a trend. The charts fill in as each week's figures are added.

UKL level, 1 October4,138.92 ft
Lake storage, 1 October219,008 AF
Net inflow, 1 Oct to 29 Oct 202648,644 AF
Water over Keno Dam, 1 Oct to 29 Oct 202643,884 AF
Change in level since 1 October−0.26 ft
Data as of29 Oct 2026

Live now, from the USGS gauges. Updates every 15 minutes while the page is open.

Upper Klamath Lake level, liveLoading
Link River flow, liveLoading
Keno flow, liveLoading

Sources: USGS gauges 11507000 (Upper Klamath Lake, Reclamation datum), 11507500 (Link River) and 11509500 (Keno). Live readings are provisional.

Lake level, 1 to 29 October 2026

Feet above sea level. Up triangle: higher than the day before. Down triangle: lower than the day before. Flat dash: no change.

Daily flows, 1 to 29 October 2026

Cubic feet per second, a measure of flow speed. Inflow is water entering the lake. Link River Dam is the lake's outlet. Keno Dam is further downstream on the Klamath River.

Inflow to lake Keno Dam release Link River Dam release

Sources: Keno Dam and Link River Dam flows are USGS daily values (gauges 11509500 and 11507500). Lake level and inflow are the Reclamation daily record in K.I.D.'s 2027 water tracker. Figures are provisional until final. Delivery charts will be added once the season's delivery records are final.

02 The year opens

WY2027 begins with the last of the 2026 season still running and a lake that finished the summer well below its April peak.

Where the lake stood on 1 October 2026

MeasureFigure
Upper Klamath Lake elevation4,138.92 ft
Upper Klamath Lake storage219,008 AF
Peak storage, WY 2027Not yet reached

The 2026 supply that carries forward

Operating within an announced supply figure is not an endorsement of it. K.I.D. is a distribution agent under its 1954 Operations Contract.

Accounts that open the year

  • Deferred Project Supply: reset to 0 AF as of 30 October 2026. Accrual begins again on 1 November from Lost River Diversion Channel return flow and F/FF Pumping Station returns to the Klamath River.
  • Flexible Flow Account: 1,931 AF on 29 October 2026. The account holds up to 35,000 AF. Water stored in the lake is released between 2 March and 30 June, and 7,000 AF is reserved for the boat dance.
03 The question for 2027

K.I.D. will publish the 2027 supply picture as it develops: snowpack through the winter, Reclamation's determination in the spring, and the season's operations as they run.

Part 2 · The 2027 operations log

04 Season timeline and log

Key dates for the year. Each row is updated when it happens.

DateMilestoneStatus
1 Oct 2026Water year 2027 opensDone
30 Oct 2026Deferred Project Supply reset to 0 AFDone
1 Nov 2026Deferred Project Supply accrual begins againUpcoming
First week of Nov 2026Emergency repairs begin: A Canal, and E Siphon under Highway 140Upcoming
Dec 2026 to Mar 2027Winter snowpack and inflow build-upUpcoming
1 Mar 20272027 irrigation season opensUpcoming
1 Apr 2027Lake elevation measured against the 2027 planUpcoming
30 Sep 2027Water year 2027 closesUpcoming
05 Maintenance and repairs

Dewatering follows the end of deliveries. The District plans a heavy maintenance season, and this section will list each job as it is scheduled and completed.

WorkTimingStatus
Dewatering after deliveries endOctober 2026Complete
Fish salvageCompleted this seasonComplete
Various inspections, including bridge infrastructureOngoingUnder way
Integrated Pest Management Plan (IPMP): rattingOngoing. Burrowing animals are removed from the system before they hibernate, to protect the infrastructure.Under way
Replace and repair turnoutsOngoingUnder way
Seasonal pump maintenanceOngoingUnder way
A Canal emergency repairStarts first week of November 2026Scheduled
E Siphon emergency repair, under Highway 140 past N. Poe Valley RoadStarts first week of November 2026Scheduled
Langeman Gate recalibrationSpring 2027Scheduled
Apply pre-emergent in canalsTiming to be confirmedPlanned
Post-irrigation season infrastructure inspectionsTiming to be confirmedPlanned
Pump winterizationTiming to be confirmedPlanned
C Hydro exercise and winterizationTiming to be confirmed. C Hydro did not operate this year.Planned
C-Hydro maintenanceTiming to be confirmedPlanned
Bridge repairsTiming to be confirmedPlanned
Automation of the B HeadgatesLater this year, timing to be confirmedPlanned
Grigsby Check improvementOn holdOn hold
#8 and #9 spill improvementOn holdOn hold

To be added: the full repair list, sequencing and dates, what patrons should expect during dewatering, whether any work needs access across private ground, and cost and funding.

Part 3 · How 2027 compares

06 Conditions going into winter

The start of the year is set by the basin's condition, and the basin enters winter in drought.

Starting position

  • On 26 October 2026, Upper Klamath Lake stood at 4,138.64 ft, about 0.20 ft below the average for the date, according to the Oregon Water Resources Department's provisional Klamath Basin Hydrology Report.

Outlook

NOAA's seasonal outlook carried drought persisting through November. The Oregon Department of Agriculture's September to November forecast leaned toward near-to-below-average precipitation, with El Niño expected to strengthen.

The updated seasonal forecast video, covering November 2026 to January 2027, is available here: Weather Seasonal Climate Forecast for November 2026 - January 2027.

None of this is a forecast of the 2027 supply. A wet winter can change the picture quickly. In 2025, one refill season followed six dry years.

07 Comparison with 2026

To come. This part will be added as the season's figures are final.

Part 4 · What the shortage cost

08 What the shortage cost

To come. This part will be added as the season's figures are final.

Part 5 · Refuge conditions

09 Refuge conditions

To come. This part will be added as the season's figures are final.

Part 6 · River conditions

10 River conditions

Adult fall-run Chinook salmon counted at the CDFW stations through 29 October 2026, from the in-season update dated 30 October 2026. Counts are preliminary.

StationStartedChinook salmonCoho salmonAdult O. mykiss (over 16 in)
Shasta River31 Aug3,560131
Bogus Creek3 Sep1301
Shovel Creek14 Sep8300
Scott River18 Sep69200
Jenny Creek30 Sep1600

Source: California Department of Fish and Wildlife, Klamath River Project Adult Fish Counting Facility 2026-2027 In-season Update, 30 October 2026. Counts do not include spawning downstream of the stations.

Part 7 · Stored water released to the river

11 Stored water released to the river

The Flexible Flow Account held 1,931 AF on 29 October 2026. In October, Keno Dam releases totaled 43,884 AF, against 48,644 AF of net inflow to Upper Klamath Lake.

Flows: USGS daily values for Keno Dam. Net inflow and the Flexible Flow Account are from the Reclamation daily record in K.I.D.'s 2027 water tracker. Provisional until final.

Reference · Rules and terms

12 Rules and regulatory frame

The framework that governs the 2027 season, drawn from public sources.

  • 2026 was the second year under the 2024 Biological Opinions from NMFS and USFWS. They moved the river compliance point to Keno Dam.
  • On 9 December 2025, Reclamation gave notice of intent to begin new formal consultation with NMFS and USFWS.
  • In June 2026, a Ninth Circuit ruling led Reclamation to reexamine its approach to consultation and long-term operations. The 2026 season continued under the existing framework.
  • H.R. 8259, the Federal Water Projects Consultation Improvement Act of 2026, was introduced in April 2026 by Rep. Cliff Bentz, with Rep. Russ Fulcher as cosponsor.
  • KWUA has described 2026 as a "bridge year" and said the consultation could be complete before the 2027 irrigation season.
  • Pub. L. 118-246, the Klamath Basin Water Agreement Support Act, requires Reclamation to fulfil farmer contracts first. Its implementation timeline runs through spring 2027.
13 Terms used on this page
Deemed available supply
The Project supply Reclamation determines is available for a season. Reclamation determines availability; it does not allocate water to K.I.D.
Deferred Project Supply
Water not used in one period that is carried forward in an account, then drawn down later in the season.
Flexible Flow Account
A store of water held in the lake between October and March and released between March and June.
Wait list
The order in which patrons are served when water is available. Seniority decides position on the wait list; it does not exempt anyone from it.
Water year
The accounting year from 1 October to 30 September, named for the year it ends.
14 Sources

Water year 2026 figures are final. WY2027 chart figures run through 29 October 2026 and are provisional until final.